Main Street Reconstruction Project Update - May 18, 2018
It has been another very productive week for JB Enterprises which has put them in a position to begin mobilization towards the next phase of reconstruction, which will be Tessier Drive to the Water Street/Simcoe Street intersection. JB Enterprises Ltd. has completed the following work for the week ending May 17th, 2018:
- The Stormwater main has been installed on Main Street from Brock Street to Tessier Drive;
- Sanitary and water services have been installed from Brock Street to Tessier Drive;
- A water meter chamber was installed on the Sewage Treatment Plant Laneway;
- Closed Circuit Television Video of the Sanitary main from Brock Street to Tessier Drive;
- Watermain installation has been completed from Beck Boulevard to Tessier Drive;
- Sub excavation has been completed to the Sewage Treatment Plant Lane from Wolfe Street and Beck Boulevard to begin rebuilding the road base. Granular placement has started at Wolfe Street and Beck Boulevard.
The following items are scheduled to be completed for the week of May 22nd to May 25th, 2018:
- Watermain flushing and testing from Beck Boulevard and Wolfe Street to Tessier Drive;
- Continue sub excavation and granular placement towards Tessier Drive for road bed reconstruction;
- Concrete curb installation from Wolfe Street to Tessier Drive;
- Sub drain installation from Wolfe Street to Tessier Drive.
JB Enterprises will NOT be working this weekend including the Victoria Day holiday.
A revised construction schedule has been released by JB Enterprises which is available on the municipal website. It has also been verbally communicated to the Town that the contractor is on schedule which is a testament to the hard work being completed by everyone involved.
Along the same lines, the businesses of Penetanguishene are remaining open during the reconstruction to serve us all, please show them your appreciation by shopping local when you can.
If you are looking to access the Launch Ramp this weekend, be advised that access will be available from either direction with potential lane restrictions.
We would like to thank you again for your patience and co-operation during this work. Should you have any questions or concerns please contact the Public Works Department at 549-7992 or visit the Town of Penetanguishene website at www.penetanguishene.ca.
Bryan Murray, P. Eng.
Director of Public Works
Town of Penetanguishene