Main Street Reconstruction Update - December 7, 2018

The work for JB Enterprises is winding down with the winter season now upon us.  There are minimal items left to complete yet JB Enterprises Ltd. has completed the following work for the week ending December 7, 2018:

  • Finishing Touches in Various Areas is Ongoing.

 

  • Temporary Line Painting Completed.

 

  • Mid Hill Seating Area Uni-lock, Plantings, and Circular Bench Completed;

 

  • Cap Stones and Site Furnishings Completed

 

The following items are scheduled to be completed for the week of December 10, 2018 to December 14, 2018:

  • Continue all final restoration in various areas.

    Thank you to everyone for your continued patience and understanding throughout the project.  Should you have any questions or concerns please contact the Public Works Department at 549-7992 or visit the Town of Penetanguishene website at www.penetanguishene.ca.


Bryan Murray, P. Eng.
Director of Public Works
Town of Penetanguishene